CASE STUDY
URC + Student Housing
University Village Towers (Greystar) - Riverside, CA
- 20 units completed in only 20 days
- We occupied 2 floors totalling in 20 units
- Each unit were 4 bedroom, 4 bath
- Scope included
• Paint
• Flooring
• New Cabinet Fronts
• Countertops
• Backsplash
• Fixtures
• Appliances
Your Preferred Student Housing Partner
20
Units in Twenty Days
20 4x4 units renovated in 20 days, just in time for students to move in to start their school year.
23,600
Square Feet of Renovations
Two floors of apartments with two different crews working simultaneously.
12,978
Square Feet of Flooring
Multi-disciplined team members ensure all work is done on time, on budget, and with the highest standards.
400
Gallons of Paint
Faster turn-around times means our clients have less days of unoccupied units.
Construction Management
With a fast turn-around we ran two crews over the 20 days, all while managing deliveries, installations, and making sure we finished with enough time for cleaning crews to make sure units were move-in ready.


Value Add
From due-diligence and helping our clients make an informed decision with regards to their acquisitions, to design-build collaboration, to adding value with upgraded materials, URC is your preferred student housing partner for turning your vision into reality.
In-House Team Give Us The Edge
URC West's in-house procurement team ensured materials arrived onsite and on time despite logistical challenges.
Strong subcontractor relationships/network means that we go where you need us
• Flooring
• Paint
• Tile
• Woodwork
Let Us Be Your Partner in Success
We want to know your needs exactly so that we can provide the perfect solution. Let us know what you want and we’ll do our best to help.